|
PLANNING
DSRSD – WWTP
Master Plan Update
WBA managed and participated in preparation of Dublin San Ramon Services District’s
wastewater treatment plant master plan. The treatment plant has a current average
dry weather flow capacity of 11.5 mgd. Projections for rates of growth in the
service area indicate that this capacity will be exceeded. Since capacity is
projected to be reached in a short time frame, the master plan update was completed
on a fast-track basis. WBA prepared an implementation plan for the planning,
detailed design and construction of improvements to meet the short timeframe
and worked in conjunction with another engineering firm to complete the necessary
technical work for the master plan. WBA is also the program manager for all
the improvements necessary at the DSRSD treatment plant. There are many distinct
projects which require planning, design and construction to satisfy the necessary
expansion and improvements. WBA has prime responsibility in ensuring that the
various projects are properly coordinated.
Town of Yountville – WWTP
Master Plan Update
The Town of Yountville, located in the Napa Valley, required a complete evaluation
of its wastewater treatment and disposal systems at current and projected future
flow rates. This study was required because the existing land disposal area,
then used to grow hay, was in the process of being converted to a new golf
course. The study involved evaluating current wastewater flows and characteristics
and projecting future flows and characteristics based on Town planning and
population projections. The capacity of the existing wastewater treatment plant
was evaluated and recommendations were made to optimize O&M costs now and
in the future. Because the Town is permitted to discharge treated wastewater
to the Napa River only during winter months, it must store effluent for winter
discharge or use the treated water for irrigation. A major portion of this
project involved optimizing the use of storage for later discharge to the river
and effluent reuse. WBA prepared and used a mathematical model to simulate
river flows, allowable dilution ratios to the river, precipitation, multiple
crop requirements, and storage requirements. The final report included recommendations,
cost breakdowns, and schedules for implementation. WBA continues to assist
the Town with implementing the recommended improvements.
City of Morgan Hill – Water
Reclamation Feasibility Study
The City of Morgan Hill retained WBA to evaluate alternatives to upgrade and
expand a regional wastewater system. As the need to commit to the regional
system was fast approaching, the City needed a thorough evaluation and preliminary
feasibility study with an associated cost estimate quickly. WBA developed a
model to determine system needs and unit costs. A key element in the project
involved estimating the size of the reservoir required to store reclaimed water
for irrigation. The model developed by WBA enabled estimation of the size of
the required reservoir, the volume of earthwork required, and the construction
cost of alternative reservoirs to accommodate changing wastewater flows and
irrigation requirements. Based on this work, the City found that it could implement
its own wastewater reclamation program at nearly the same cost as its share
of the regional plant.
SKF – Sludge
Dewatering Study
WBA conducted a Sludge Dewatering Study for SKF to estimate the onsite sludge
drying bed dewatering capacity and to evaluate a supplemental mechanical dewatering
system to handle the sludge production in the winter months when the onsite
sludge drying beds are not operational. The study concluded that a supplemental
mechanical dewatering system is a viable and cost effective means for the District
to effectively manage the sludge production during the winter months.
Based on one of the
recommendations as adopted by the District, WBA developed an
onsite pilot study program and coordinated with two sludge dewatering
equipment manufacturers, one for a belt press system and one
for a centrifuge system, to perform onsite sludge dewatering
pilot studies. Based on the results of the pilot studies, WBA
prepared a “Sludge Dewatering Pre-engineering Study” to
define the general requirements of the sludge dewatering system
and to evaluate the life cycle costs of the belt press and centrifuge
systems. The study concluded that a centrifuge system is the
recommended alternative for the District.
DESIGN
Livermore Water Reclamaion Plant –Plant Expanion
WBA led the design f a 2.25 mgd, Phase 5 expansin of the Livermore Water Relamation
Plant. This project involved expansion or upgrading of the major treatment
units and the associated process and utility piping and pumping system. In
addition, the project included the planning and design of a completely new
digested sludge system with high-rate facultative sludge lagoons and two-stage
paved drying beds. Finally, the project included the design of a new administration
and control building, a new maintenance building, retrofit of the original
operations building to serve as a laboratory, and a new entrance road surrounded
by a park-like area featuring ornamental and irrigation uses of reclaimed water.
Team architects assisted in gaining acceptance of the project by the City design
review commission.
City
of Millbrae –Plant Improvements
The city of Millbrae selected WBA to design several major improvements to their
wastewater treatment plant. The improvements consisted of modernizing the headworks
and influent pumping facilities, rehabilitating the primary and secondary sedimentation
units and replacing the sludge dewatering centrifuges. The headworks and influent
pumping facilities modifications consisted of replacing the single, variable
speed pump, two fixed speed horizontal centrifugal pumps and outdated comminutors
and screening devices with three vertical pumps and three hydraulically operated
comminutors. The primary sedimentation units modifications included new roofs,
new chain drives and temporary structural supports to hold the tanks in place
while the roofs were being replaced. WBA designed the replacement of the rotating
screens in the secondary sedimentation tanks with fiberglass baffles. Modifications
to the tilting weir skimmers in the cells of the chlorine contact tank enabled
the rotating skimmer to be eliminated, thereby increasing the hydraulic capacity
of the entire plant from 7 mgd to 10 mgd. The sludge dewatering centrifuges
were replaced with a belt filter press, and the building housing the centrifuges
was modified to accommodate the new equipment as well as to shield the operators
from the weather and freeway noise. Heavy rainstorms that occurred during the
1992-93 rainy season were a major test of the improvements. The success of
the improvements was proven by the fact that, for the first time, the City
did not experience any NPDES violations during a heavy rainstorm.
FSSD –2002
Maintenance Project
WBA designed numerous wastewater treatment plant and pump station modifications
for the Fairfield Suisun Sewer District as part of the 2002 Maintenance Project.
Modifications included installing a second pH meter with associated control
improvements to control influent pH, analyzing and upgrading the variable speed
RAS pumping system, replacing existing raw sewage pumps and installing new
VFDs, analyzing and modifying the sludge holding tank mixing system, locating
and repairing leaks in a buried aeration header, and installation of a security
system at the WWTP site.
SKF –Sludge
Dewatering Facility
WBA completed a sludge dewatering study for SKF that recommended the installation
of a centrifuge. Based on this study, WBA prepared the procurement documents
for the District to pre-purchase a centrifuge unit with a capacity to dewater
200 gpm of feed sludge at 2% solids concentration. The selection and award
of the purchase order was based on the evaluated costs which accounted for
the equipment cost, the projected system performance, and the 10-year projected
O&M costs. SKF purchased and took delivery of the centrifuge based on this
procurement process.
WBA designed the facilities
needed to complete the sludge dewatering system using the prepurchased
centrifuge. The facilities include a new centrifuge building,
a sludge feed pump, a polymer preparation and feed system, a
sludge cake pump system and associated civil, mechanical, control
and elecctrical systems. The design of the system includes allowance
for installation of a second centrifuge unit in the future.
The above projects
are representative of our experience in this area.
If you would like additional information on these, or other projects that
we have completed, please contact
us.
For detailed descriptions
of representative projects in our other areas of expertise, click
below on the category you are interested in:
Recycled Water:
Wastewater:
Water Supply:
Specialized
Areas:
|