Wastewater Treatment Projects:
Disinfection
 
Projects
Clients
Presentations
About Us

Contact Us

Career Ops


DSRSD - UV System Expansion
WBA developed a plan to increase the permitted capacity of the DSRSD UV system from 1 to 3 mgd. This work was needed to increase the capacity of the UV and microfiltration (MF) recycled water treatment facilities to 3 mgd. The permitted capacity of the UV system was increased by completing hydraulic modifications, installing additional UV modules, and modifying the control of the UV system. Fewer modules than anticipated were added because previous system testing by WBA demonstrated that hydraulic and UV control modifications would increase the capacity of the UV system and still achieve the regulated virus reduction. WBA completed the design of the above modifications, and managed the implementation of the modifications.

City of Sunnyvale - UV Disinfection Feasibility Study
WBA evaluated disinfection alternatives to the City of Sunnyvale’s existing chlorination system. The study included laboratory analyses of UV disinfectability parameters of the City’s effluent under various operating conditions, and sizing and cost analysis for different types of disinfection systems for various combinations of recycled water production and disinfection for Bay discharge. The analysis included required UV dosages, system sizing, capital and operation cost estimates, and discussion of related non-cost issues.

FSSD – UV Disinfection Analysis
WBA evaluated UV disinfection alternatives for retrofitting the Fairfield-Suisun Sewer District’s (FSSD) chlorine contact tanks. The District was interested in determining the feasibility of eliminating gaseous chlorine from its treatment process. The analysis included evaluation of District filtered effluent water quality at different times of year to allow the District to take advantage of the elevated ultraviolet transmittance of its effluent. Three types of UV systems were evaluated to determine the most cost-effective means of expanding the District’s disinfection capacity and examine the feasibility of eliminating chlorine from the treatment process.

City of HaywardDisinfection Facilities
The City of Hayward selected WBA to replace its disinfection systems with sodium hypochlorite. Both the effluent disinfection system and the plant wash water facilities required conversion. The plant’s average flow was about 9 MGD and peak hydraulic capacity was about 40 MGD. The City originally had hoped to use the existing chlorine storage building slab for the hypochlorite facilities and build a new building. WBA evaluated the foundation conditions and determined that the bay mud underlying the slab would be subject to liquifaction during an earthquake. Based on our recommendations, the City authorized the design of a new building. WBA provided the plans and specifications for installation of the sodium hypochlorite equipment. WBA provided construction period office engineering and assistance to the City in their application to the Federal Emergency Management Agency to fund half the project costs.

WCWDDisinfection Facilities
The West County Wastewater District (WCWD) retained WBA to rehabilitate its effluent disinfection system by converting from gaseous chlorine to sodium hypochlorite. The plant’s average flow was about 12 MGD and peak hydraulic capacity was about 33 MGD due to its ability to store excess flows in flow equalization basins. Shortly after initiating the design, the District experienced a severe wet weather event necessitating diversion of treated effluent through an abandoned outfall. Since the outfall had been abandoned, the District had no regular means of dechlorinating the effluent prior to discharge. For the duration of the winter, they used a rented bisulfite system. As a result of that experience, they amended the WBA design contract to include installation of a bisulfite feed system. We were able to use space in an existing chemical building by replacing an abandoned caustic tank with a new bisulfite storage tank. WBA completed contract documents to complete all these tasks.

Oro Loma Sanitary DistrictDisinfection Facilities
The Oro Loma Sanitary District decided to rehabilitate its effluent disinfection system by converting from gaseous chlorine to sodium hypochlorite. The plant’s average flow was about 12 MGD and peak hydraulic capacity was about 100 MGD. The District had decided to expedite the project by using in-house staff to design the base slab and elected to pre-purchase the bulk storage tanks and the chemical feed pumps. The District retained WBA to do the process design, review the structural design and modify it to accommodate pipe chases for the piping. WBA provided the pre-purchase specifications and the plans and specifications for installation of the sodium hypochlorite equipment. The process design was complicated by the fact that some of the effluent was used for golf course irrigation. The plant had a separate contact tank for the irrigation water that needed additional chlorination and WBA’s design allowed the District to disinfect the irrigation water with the same feed pumps as was used for the other effluent.

USDOdor Scrubber Upgrade
The Union Sanitary District (USD) retained WBA to develop design documents to modify its 17 chlorine mist type scrubbers to use liquid-only spray nozzles in place of the existing liquid and air spray nozzles. By eliminating the use of compressed air, the District avoided the capital cost of replacing its existing maintenance intensive compressors, and will realize significant savings by not operating the four 200 hp compressors.
The design consists of developing a distribution system to deliver the concentrated sodium hypochlorite to all scrubbers, new control panels to control the addition of concentrated sodium hypochlorite to each scrubber, and modification to the scrubber nozzles and feed piping to deliver the sodium hypochlorite solution to the scrubber ducting.


The above projects are representative of our experience in this area.
If you would like additional information on these, or other projects that
we have completed, please contact us.

For detailed descriptions of representative projects in our other areas of expertise, click below on the category you are interested in:

Wastewater:

Recycled Water:

Water Supply:

Alternative Energy:

  • Economic Evaluations
  • Technology Selection
  • Waste to Energy Services (Cogeneration)

Specialized Areas:

 

 

Home - Projects - Clients - Presentations - About Us - Contact Us - Career Opportunities
Copyright 2002, Whitley Burchett & Associates