SCADA
 
Home
Projects
Clients
Presentations
About Us

Contact Us Career Opportunities

 


DSRSDWWTP SCADA System Design
WBA developed the design documents to replace the District’s existing main control panel with a SCADA system. To ensure that a qualified system integrator was retained to install the SCADA system, WBA developed and managed an RFP process to award the project. The RFP selection criteria were based on qualifications in addition to price so that the District was not obligated to select the system integrator with the lowest price. The design documents were developed to use design-build strategies where appropriate to primarily take advantage of the knowledge of the system integrator, and to minimize risk to the District. The key design elements included defining the number and location of the PLCs and HMIs, the HMI and PLC network design, the number and location of over 700 I/O points, the description of the control strategies, description of the SCADA screens, defining the reuse of existing conduits and the installation of new conduits, and the sequencing plan to minimize disruption of operations during the installation of the SCADA system.

DSRSD
WWTP SCADA System Installation Management

WBA managed the contract with the system integrator, Control Manufacturing Company (CMC), to replace the existing main control panel with a SCADA system. Tasks included shop drawing review, review of the SCADA system screens, witnessing the system factory test, management of communications with the system integrator, negotiation of change orders, observation of the system installation, review and coordination of system cutover plans, monitoring of field testing of the system, assistance with system start-up, training of District staff, and reviewing progress payment requests.

DSRSDStage 4 Expansion SCADA System Installation Management
The existing WWTP SCADA system needed to be modified as part of the Stage 4 WWTP expansion project for DSRSD. Because of the success of the initial installation of the WWTP SCADA system, the District selected WBA to manage a separate contract with the same system integrator (CMC) to modify the SCADA system. WBA also developed a contract and negotiated a fee with CMC to complete the necessary SCADA modifications. For the installation management phase, tasks for WBA included shop drawing review, review of the SCADA system screens, witnessing the system factory test, management of communications with the system integrator, negotiation of change orders, observation of the system installation, review and coordination of system cutover plans, monitoring of field testing of the system, assistance with system start-up, and reviewing progress payment requests.

FSSDWWTP SCADA System
A WBA employee managed the process to design and install a SCADA system to replace the Fairfield-Suisun Sewer District’s (FSSD) plant process computer system while he was employed at FSSD as the engineering and operations manager. An RFP process was developed and used to primarily allow the District to account for technical qualifications in selecting a contractor for the project, and to save time and money. The RFP contained the criteria for reviewing proposals, and the technical requirements for the project, which required the contractor to design, furnish, and install all items to make a complete and operable system. The technical requirements consisted of a blend of performance specifications and detailed specifications. The scope of work generally consisted of furnishing, installing, and programming PLCs and HMIs, a new fiber optic cable system to network PLCs and the HMIs, wiring as needed to connect the I/O points to the PLCs, and a new SCADA software package. The contractor also had to design, plan, and schedule the work to minimize interference with the operation of the existing plant process computer system.

DSRSWater System SCADA Expansion Design and Installation Management
WBA designed and managed the installation of the SCADA System Expansion based on the SCADA System Master Plan completed by WBA. The projects included installation of data concentrators for water and recycled water facilities in Eastern Dublin and Dougherty Valley. The data concentrators communicate with their applicable facilities using 900 MHZ spread spectrum radios. The data concentrators are responsible for sending and transmitting control signals for their facilities so that if communications with the central site failed, control signal communications would be maintained. Modifications at the central site to improve system reliability will include installation of an ethernet network, an additional HMI as a back-up, and a UPS system. The SCADA screens will also be modified to improve monitoring and control.


The above projects are representative of our experience in this area.
If you would like additional information on these, or other projects that
we have completed, please contact us.

For detailed descriptions of representative projects in our other areas of expertise, click below on the category you are interested in:

Recycled Water:

Wastewater:

Water Supply:

Specialized Areas:

 

 

Home - Projects - Clients - Presentations - About Us - Contact Us - Career Opportunities
Copyright 2002, Whitley Burchett & Associates